OpenSling Assembly Overview¶
This is a high-level assembly guide for the current OpenSling reference distiller. It is inspired by the public Slingshot mechanism, but it is not presented as a factory clone or a certified potable-water product.
Reference Build Scope¶
The current reference build assumes:
- a low-pressure vapor-compression distillation loop
- aggressive heat recovery on feed, product, and blowdown streams
- a custom frame plus pressure-bearing wet hardware
- removable non-pressure custom parts for routing, guarding, mounting, and instrumentation
Before You Build¶
Do not start with contaminated water. First assemble and commission with clean water so that you can:
- pressure test the shell and fittings
- validate controls and shutdown logic
- characterize leaks and parasitic heat loss
- establish baseline pressure and temperature behavior
Builder Flow¶
If your goal is to actually get parts on a bench instead of just reading theory, use this order:
- Read the Alpha Buy List and Missing Pieces.
- Order the
buy nowparts first. Those are the lowest-regret purchases in the current repo state. - Print or machine the non-pressure parts in the Fabrication Pack.
- Build the frame, drains, feed-side routing, and instrument mounts before buying the pressure core.
- Hold the expensive geometry-dependent parts until the pressure shell, heater mount, and compressor operating point are frozen.
- Hydrotest with water before any heated or dirty-water run.
The current OpenSling docs are honest about what is still missing. That is better than pretending a pressure vessel or heater package is already settled when it is not.
Assembly Sequence¶
-
Build the frame and mounting surfaces. Mount the wet section low and the controls section high. Leave service clearance around the compressor, heater, knock-out pot, and sample ports.
-
Assemble the feed, preheat, and blowdown loop. Install the feed tank, coarse strainer, preheater, blowdown needle valve, drain routing, and collection vessel before the distillation core goes in.
-
Assemble the evaporator/condenser core. Build the main pressure shell, internal tube bundle, service ports, relief provisions, and insulation interface. Pressure-bearing parts require hydrotest before thermal commissioning.
-
Install demister and mist protection upstream of compression. Add the knock-out/demister stage between the steam chest and the compressor so entrained droplets do not become compressor damage.
-
Mount the vapor-compression stage. Install the side-channel/regenerative blower or chosen compressor with isolation mounts, a short service loop, and temperature/pressure instrumentation on both sides.
-
Route the product condensation and recovery lines. Direct condensed product into clean-side tubing, then through any polishing or storage-protection steps you plan to test.
-
Install startup heat and controls. Add the startup heater, contactor or relay hardware, level sensing, pressure sensing, and emergency stop logic. Keep wet and electrical zones visually separated.
-
Fit custom support and routing parts. Install the printed guards, cable guides, hose separators, panel blanks, and mounting brackets from the Fabrication Pack only after major hardware alignment is fixed.
-
Hydrotest and leak-check. Test the pressure boundary with water, not steam, first. Record pressures, dwell times, and any gasket movement.
-
Commission with clean water, then move to dirty-water trials. Establish stable startup, steady-state compression, blowdown control, and product routing before exposing the machine to fouling loads.
Minimum Commissioning Data¶
- feed, shell, and compressor pressures
- steam-side and product-side temperatures
- startup time to stable production
- blowdown rate
- product conductivity or other basic quality screen
- treated volume before noticeable fouling or drift
Build Philosophy¶
The goal is not to hide complexity inside a sealed box. The goal is to create a machine that can be opened, sampled, cleaned, modified, and understood by the next builder.